Project Status: In Design
Project Overview
The Healthy Infrastructure Plan (HIP) identified three corridors for increasing trails to connect residents and visitors to parks, school, alternative transportation infrastructure, etc. These trails will utilize utility corridors, on-street bike paths, shared use paths adjacent to streets and creek areas. The objective of a corridor through Castle Hills will be connections to the robust trails in adjacent communities such as Carrollton, Plano, and The Colony, as well as to the majority of Lewisville including the Green Centerpiece. The Castle Hills Corridor Trail Phase I was included in the bond package for parks and trails approved by voters in 2024.
The City of Lewisville selected McAdams to provide surveying and landscape architecture services to prepare a schematic design for the trial. The design will be based on guidelines as set forth in the HIP, 2024 bond election proposed projects document, and Parks and Recreation trail design standards. The site of the proposed improvements is Phase I of the Castle Hills Trail Development for the southernmost portion of the corridor running from Windhaven Parkway east to the utility easement, then north along the easement to the sports fields. The project will include a 12’ wide trail, wayfinding signage, trailhead(s), park furniture and shade, where possible.
A key component of achieving our vision for this trail is to engage with our partners. This will be achieved through a deliberate effort by involving the community in our decision-making process. We will work with our residents to help reduce project risk and builds long-term trust. McAdams and the City will ensure that the needs of the people whoaffect or are affected by this project are heard and integrated into our goals.
Join the Lewisville Parks and Recreation Department to learn more about the trail and project timeline. Engagements will be held on Aug. 29, from 10-11:30 a.m., at the Lewisville Jamatkhana, 2560 FM 544 and Sept. 1, from 6-7:30 p.m., at Lake Avalon Park, 806 Lady of the Lake.
Trail Timeline
Summer 2025: Site inventory & field analysis begins.
Summer-Fall 2025: Geometrics and GIS study completed.
Fall 2025-Spring 2026: Schematic design developed.
Spring 2026: Schematic designed approved.
Summer 2026: Public engagement meetings held on Aug. 29 and Sept. 1.
Fall 2026-Winter 2027: Development of construction plans, pending approval.